Mugla Water Supply Feasibility Assessment

  • Country: Turkey

  • Client: Stantec (lead consultant), for the European Bank for Reconstruction and Development (EBRD)

  • Beneficiary: Muğla Water and Sewearage Administration(MUSKİ)

  • Period: September 2025–April 2026

  • Mojo EC’s Role: Sub-consultant providing expert services for procurement and contract strategy

Summary
Mojo EC supported EBRD, through Stantec, in appraising a proposed investment programme to reduce non-revenue water in Muğla's water supply and distribution system. The study established the technical and financial feasibility of the programme and defined a Priority Investment Programme for EBRD financing.

Scope of services

  • Review of water supply projects including a water transmission line and 6 projects for 3 municipalities of Mugla (Koycegiz, Dalyan, Ortaca)

  • Procurement and contract strategy

  • Options analysis for Works vs Performance Based Contracts

  • Packaging of works and consultancy services as well as other technical cooperation programmes

  • Assessment of operational and institutional capacity gaps and proposing measures

  • Risk register